CASE STUDY

Weeks Marine

Jersey City, New Jersey
LOCATION
River Terminal: Barge Unloading
INDUSTRY

Key Insights

Dredging was required to create enough depth at the Hudson River for cranes and other equipment used in building a new bridge in New York City. Weeks Marine used a custom barge-mounted TeleStacker Conveyor to cap the dredge site, with sand and stone coming from the Port of Coeymans.

Weeks Marine - Jersey City,NJ (July 2014)_097-1

More Projects & Resources

057: Gotham Aggregates_Newark NJ_TS Barge Loading_014-1

Gotham Aggregates Cuts Shipping Costs by 35% with Barge-Lading TeleStacker® Conveyor

062: Knife River morse-bros-barge-telestacker-conveyor-by-superior-industries-2

Knife River Shifts to Barge Transport, Saving an Estimated $1 Million in Seven Months

 

 

067: TeleStacker Conveyor at Pontchartrain-3-1

Flexibility on the Mississippi: Pontchartrain Materials' Super Custom, Barge-Mounted Conveyor